The RES market in Greece began to take shape in the mid-1990s, with an active role played by various small investors.

The ELLAKTOR Group of companies (former ELLINIKI TECHNODOMIKI TEV S.A.) established project companies in 2000 and entered the shareholder structure of other companies that had been active in the area of RES already in 1997. One of these companies, TETRAPOLIS AIOLIKA PARKA S.A., absorbed project companies and, following share capital increases, its current shareholder structure was formed in March 2008. Further, during the same period, TETRAPOLIS AIOLIKA PARKA SA was renamed ELLINIKI TECHNODOMIKI ANEMOS SA.

The milestones in the development of the company are the following:

  • 2003

    The first wind farms with 9 MW installed capacity are commissioned (Lesvos)

  • 2006

    A wind farm with 13.6 MW installed capacity is commissioned (Cephalonia)

  • 2008

    The individual special purpose companies already operating wind farms are merged and absorbed by the Company.

  • 2009

    A wind farm with 32.2 MW installed capacity is commissioned (Cephalonia)

  • 2010-2013

    The portfolio of the Company’s projects (in terms of installed capacity) is almost tripled, and now amounts to 171 MW

  • 2014

    Listing of the Company on the Athens Stock Exchange.

  • 2015

    Two wind parks of 36.8 MW total power capacity are set on operation mode. (Troizinia and Evros region)

208

MW in operation

57

MW under construction

784

MW Pipeline